2020年系统集成项目管理工程师真题(15)70、 The main direction of Integration of Industrialization and Informatization is ().A. internet plusB. big dataC. cloud computingD. intelligent manufacturing参考答案:D71、() is

引号

2020年系统集成项目管理工程师试题(15)

70、 The main direction of Integration of Industrialization and Informatization is ().

A. internet plus

B. big data

C. cloud computing

D. intelligent manufacturing

参考答案:D

71、() is called the gateway of network security, which is used to identify what kind of data packets can enter the enterprise intranet. 

A. Anti-virus software

B. Trojan horse

C. Secret key

D. Firewall

参考答案:D

72、A () is a graph that shows the relationship between two variables. 

A. histogram

B. flowchart

C. scatter diagram

D. matrix diagram

参考答案:C

73、( ) is the process of identifying individual project risks as well as source of overall project risk, and documenting their characteristics, 

A. Identify Risks

B. Monitor Risks

C. Implement Risk Responses

D. Plan Risk Management

参考答案:A

74、As one of the core technologies of block chains, () refers to the fact that transaction accounting is performed by multiple nodes distributed in different places, and each node records a complete account, so they can participate in the supervision of transaction legitimacy and testify for it together. 

A. intelligent contract

B. consensus mechanism

C. asymmetric encryption technology

D. distributed accounts

参考答案:D