信息系统中级教材pdf 信息系统答案




2016上半年信息系统项目管理师上午综合知识真题与答案汇总2016上半年信息系统项目管理师英文题与参考答案71、After acceptance and formal transfer of information systems to customers it has entered the stage of ()A、preparationB、operation and mainte

2016上半年信息系统项目管理师上午综合知识试题与答案汇总
2016上半年信息系统项目管理师英文题与参考答案
71、After acceptance and formal transfer of information systems to customers it has entered the stage of ()
A、preparation
B、operation and maintenance
C、development
D、extinction
B
72、()a method of obtaining early feedback on requirements by providing a working model of the expected product before actually building it
A、prototype
B、object oriented
C、structured method
D、iterative method
A
73、The scope management plan is how the team will prepare the()a document that includes
descriptions of create the WBS, verify completion of the project deliverables, and control requests for changes to the project scope.
A.project charter
B.project scope goal
C.project budget
D.project scope statement
D
74、( ) is one of the tools and techniques of Sequence Activities
A.Decomposition
B.Fishbone Diagram
C.Precedence Diagramming Method
D.Expert Judgment
C
75、The schedule management plan is a component of the project management plan The
schedule management plan may be formal or informal, highly detailed or broadly framed, based upon the () of the project, and includes appropriate control thresholds.
A.goals
B.values
C.needs
D.level
C