1、estimating schedule activity costs involves developing an () of the cost of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives.for example,in mostapplication areas,additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product oprations.the cost estimating process considers whether the expected savings can offset the cost of the additional design work.cost estmates are generally expressed in units of () to facilitate comparisons both within and across projects.the (请作答此空) describes important information about prject requirement that is considered duing cost estimating.
A、 project scope statement
B、 statement of work
C、 project management plan
D、 project policy
答案:A
答题解析:
2、() 体现了项目计划过程的正确顺序
A、 范围规划— 范围定义— 活动定义— 活动历时估算
B、 范围定义— 范围规划— 活动定义— 活动排序— 活动历时估算
C、 范围规划— 范围定义— 活动排序— 活动定义— 活动历时估算
D、 活动历时估算— 范围规划— 范围定义— 活动定义— 活动排序
答案:A
答题解析:项目范围管理包括的过程,依先后顺序排列如下:1)范围计划制定(或称范围规划);2)范围定义;3)创建工作分解结构;4)范围核实;5)范围变更控制。而项目时间管理包括的过程,依序排列为:6)活动定义;7)活动排序;8)活动资源估算;9)活动历时估算;10)制定进度计划;11)进度计划控制。正常情况下,先确定项目的范围,在此基础上再对项目的时间进行管理。
3、在计划编制完成后,项目团队认为所制定的进度时间太长,分析表明不能改变工作网络图,但该项目有附加资源可以利用,项目经理采用的最佳方式是()
A、 快速追踪项目
B、 引导一项Monte Carlo 分析
C、 利用参数估算
D、 赶工
答案:D
答题解析:缩短项目进度的技术主要如下:1)变更项目范围:主要是指缩小项目的范围;2)赶工:是一种通过分配更多的资源,达到以成本的最低增加进行最大限度的进度压缩的目的,赶工不改变活动之间的顺序;3)快速追踪:也叫快速跟进,是指并行或重叠执行原来计划串行执行的活动。快速追踪会改变工作网络图原来的顺序。参数估算和Monte Carlo 分析与进度压缩没有直接关联。
1、estimating schedule activity costs involves developing an () of the cost of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives.for example,in mostapplication areas,additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product oprations.the cost estimating process considers whether the expected savings can offset the cost of the additional design work.cost estmates are generally expressed in units of () to facilitate comparisons both within and across projects.the (请作答此空) describes important information about prject requirement that is considered duing cost estimating.
A、 project scope statement
B、 statement of work
C、 project management plan
D、 project policy
答案:A
答题解析:
估算计划活动的成本涉及估算完成每项计划活动所需资源的近似成本,成本估算包括设别和考虑各种成本计算方案。例如:在多数的应用领域,普遍在设计阶段多做些额外工作以降低在执行阶段和产品运行时的潜在成本。成本估算过程考虑预期的成本节省是否能够弥补额外设计工作的成本。成本估算一般是以货币单位表示,以利于在项目内和项目间进行比较,项目范围说明书描述了项目的商业要求、理由、需求和当前边界,它提供了关于在成本估算时必须考虑的项目需求的重要信息。
2、() 体现了项目计划过程的正确顺序
A、 范围规划— 范围定义— 活动定义— 活动历时估算
B、 范围定义— 范围规划— 活动定义— 活动排序— 活动历时估算
C、 范围规划— 范围定义— 活动排序— 活动定义— 活动历时估算
D、 活动历时估算— 范围规划— 范围定义— 活动定义— 活动排序
答案:A
答题解析:项目范围管理包括的过程,依先后顺序排列如下:1)范围计划制定(或称范围规划);2)范围定义;3)创建工作分解结构;4)范围核实;5)范围变更控制。而项目时间管理包括的过程,依序排列为:6)活动定义;7)活动排序;8)活动资源估算;9)活动历时估算;10)制定进度计划;11)进度计划控制。正常情况下,先确定项目的范围,在此基础上再对项目的时间进行管理。
3、在计划编制完成后,项目团队认为所制定的进度时间太长,分析表明不能改变工作网络图,但该项目有附加资源可以利用,项目经理采用的最佳方式是()
A、 快速追踪项目
B、 引导一项Monte Carlo 分析
C、 利用参数估算
D、 赶工
答案:D
答题解析:缩短项目进度的技术主要如下:1)变更项目范围:主要是指缩小项目的范围;2)赶工:是一种通过分配更多的资源,达到以成本的最低增加进行最大限度的进度压缩的目的,赶工不改变活动之间的顺序;3)快速追踪:也叫快速跟进,是指并行或重叠执行原来计划串行执行的活动。快速追踪会改变工作网络图原来的顺序。参数估算和Monte Carlo 分析与进度压缩没有直接关联。