历年软考试题:2019年5月信息系统项目管理师 模拟二上午
摘要:对于【信息系统项目管理师】软考考试而言,试题无疑是最重要的学习资料之一。在软考备考过程中,吃透所考知识点、熟悉出题思路,对我们提升分数的效果是最明显的,通过试题反复练习,还可以查漏补缺。今天,给大家带来【信息系统项目管理师】部分试题的详解,一起来看看吧~1、Configuration management system can be used in defining approval lev
1、Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes.( ) is not a project configuration management tool.
A、 Rational Clearcase
B、 Quality Function Deployment
C、 Visual SourceSafe
D、 Concurrent Versions System
答案:B
答题解析:
配置管理的目的在于运用配置标识、配置控制、配置状态统计和配置审计,建立和维护工作产品的完整性。常用的配置管理工具有Visual SourceSafe、Rational Clearcase,以及Concurrent Versions System等。
2、Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( ) , and schedule control by order.
A、 activity duration estimating, schedule developing, activity resource estimating
B、 activity resource estimating, activity duration estimating, schedule development
C、 schedule developing, activity resource estimating, activity duration estimating
D、 activity resource estimating, schedule developing, activity duration estimating
答案:B
答题解析:
项目时间管理包括使项目按时完成所必需的管理过程。进度安排的准确程度可能比成本估计的准确程度更重要。考虑进度安排时要把人员的工作量与花费的时间联系起来,合理分配工作量,利用进度安排的有效分析方法来严格监视项目的进展情况,以使得项目的进度不致被拖延。
项目时间管理过程包括:活动定义、活动排序、活动的资源估算、活动历时估算、制订进度计划及进度控制6个步骤。
以上6个步骤具有先后顺序,因此选择“活动的资源估算”、“活动历时估算”、制订进度计划,所以选B。
A. 活动历时估算 制订进度计划 活动的资源估算
B. 活动的资源估算 活动历史估算 制订进度计划
C. 制订进度计划 活动的资源估算 活动历时估算
D. 活动的资源估算 制订进度计划 活动历时估算
3、Many useful tools and techniques are used in developing schedule. ( )is a schedule network analysis technique that modifies the project schedule to account for limited resource.
A、 PERT
B、 Resource levelling
C、 Schedule compression
D、 Critical chain method
答案:D
答题解析:
许多有用的工具和技术被用于开发进度中,( )是一种进度网络分析技术,通过修改项目进度来考虑资源限制。
A. PERT B. 资源平衡
C. 进度压缩 D. 关键链法
软考资料: 2024年软考论文范文> 软考考试核心重点难点汇总> 查看更多>
备考刷题:章节练习+每日一练> 软考历年试题+模拟题>查看更多>