1、( ) is one of the quality planning outputs.
A、 Scope base line
B、 Cost of quality
C、 Product specification
D、 Quality checklist
答案:D
答题解析:
2、Which of the following statement related to PMO is not correct? ( ).
A、 The specific form, function, and structure of a PMO is dependent upon the needs of the organization that it supports.
B、 One of the key features of a PMO is managing shared resources across all projects administered by the PMO.
C、 The PMO focuses on the specified project objectives.
D、 The PMO optimizes the use of shared organizational resources across all projects.
答案:C
答题解析:
3、The inputs of developing project management plan do not include ( ).
A、 project charter
B、 stakeholder management strategy
C、 project scope statement
D、 outputs from planning processes
答案:B
答题解析:

1、( ) is one of the quality planning outputs.
A、 Scope base line
B、 Cost of quality
C、 Product specification
D、 Quality checklist
答案:D
答题解析:
( )是制定项目质量管理计划过程的成果之一。
A.范围基线 B.质量成本 C.产品规范 D.质量检查表
2、Which of the following statement related to PMO is not correct? ( ).
A、 The specific form, function, and structure of a PMO is dependent upon the needs of the organization that it supports.
B、 One of the key features of a PMO is managing shared resources across all projects administered by the PMO.
C、 The PMO focuses on the specified project objectives.
D、 The PMO optimizes the use of shared organizational resources across all projects.
答案:C
答题解析:
下列各项中,哪一个有关PMO的说法是错误的? ( )。
A.PMO的具体形式、职能和结构取决于它支持的组织的要求
B.PMO的关键特征之一是在所有PMO管理的项目之间共享和协调资源
C.PMO关注于特定的项目目标
D.PMO对所管理的所有项目共享资源的使用进行优化
3、The inputs of developing project management plan do not include ( ).
A、 project charter
B、 stakeholder management strategy
C、 project scope statement
D、 outputs from planning processes
答案:B
答题解析:
制定项目管理计划的输入不包括 ( ) 。
A.项目章程 B.干系人管理策略
C.项目范围说明书 D.计划过程输出